Does anyone know if it's possible with Jira to cover the following scenario?
- The team estimates the items in its backlog in story points
- The backlog is prioritized
- The backlog is handled like a Fifo queue; the team works on the highest items first
- The team has a known velocity, predicted by the last days' weather method
Because every item is estimated and velocity and priority are known, I'd be able to show the estimated time when an item is finished. The calculation could be updated dynamically, for example when someone reprioritizes an item or something gets finished.
The easiest solution I can think of is to simply add another field to each item which is then shown in the Kanban view. Has anyone experience with something like this?