You are managing a project with a total planned budget of $100,000. To date, you have actually spent $41,000. When you look at all the activities you have completed to date, you see that you planned to spend $33,000 on the activities you've actually completed. And when you look at your original baseline plan, you see that your budget was planned to spend $50,000 by this date. Determine the PV, AC, EV, and BAC.

I Was able to calculate PV, AC, BAC correctly in this example but Earned Value.

I think to date we planned to complete 50% of the project hence PV = $50,000 but how to calculate EV in this example. Sorry I am new to this and planning to attempt CAPM exam soon.

FYI, https://courses.edx.org/courses/course-v1:RITx+PM9001x+1T2019/courseware/fa7be505e8bc46e9821097a1b19ba66e/1f591555a6154a06a63152ddfd2bbc0f/2?activate_block_id=block-v1%3ARITx%2BPM9001x%2B1T2019%2Btype%40poll%2Bblock%403cbbecef96774c20ab30b0e164dbaa77

  • 1
    EV is what you have completed. Read the.problwm again. – David Espina May 5 '19 at 18:18

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Browse other questions tagged or ask your own question.