I have a Microsoft Project 2016 file that looks something like this:

Calendar Project (Summary)
    Design (Summary)
        Collect Requirements (Task)
        Design Schema (Task)
        Design Complete (Milestone)
    Implementation (Summary)
        Feature #1 (Task)
        Feature #2 (Task)
        Feature #3 (Task)
        Implementation Complete (Milestone)
    Testing (Summary)
        Test Feature #1 (Task)
        Test Feature #2 (Task)
        Test Feature #3 (Task)
        Testing Complete (Milestone)

Right now I'm in the middle of the "Implementation" phase. I just added another "Demo" Summary and Tasks, as seen below:

Calendar Project (Summary)
    Design (Summary)
        Collect Requirements (Task)
        Design Schema (Task)
        Design Complete (Milestone)
    Implementation (Summary)
        Feature #1 (Task)
        Feature #2 (Task)
        Feature #3 (Task)
        Implementation Complete (Milestone)
    Demo (Summary)
        Demo Implementation (Task)
        Modify Implementation (Task)
        Demo Complete (Milestone)
    Testing (Summary)
        Test Feature #1 (Task)
        Test Feature #2 (Task)
        Test Feature #3 (Task)
        Testing Complete (Milestone)

All Summaries, Tasks, and Milestones have a Task Mode of Auto Scheduled, and the Tasks are linked sequentially via Predecessors. The Start and Finish dates for all affected Summaries and Tasks did update automatically and are accurate. However, the highest level Summary, "Calendar Project", still shows the same % Complete as it did before, even though the Finish date has increased significantly due to the "Demo" phase being added. I would expect this % Complete to decrease since the Finish date increased. I have tried clicking the "Update Project" and "Calculate Project" buttons and they are not updating this % Complete. What is going on here and how can I fix it? Thank you.

EDIT: As a test I increased the "Demo Implementation" Task from 1 day to 100 days, which almost doubles the full timeline of the project, but the % Complete for the "Calendar Project" Summary only goes from 54% to 41%. So that % Complete is being updated, just not significantly. Maybe this is because I'm in the middle of the project?