I have multiple tasks that have different durations that I want to start at different times from a go live date, i.e. finish date for an entire project.
For example: Project must finish on 01 Dec 2019. Task 1, duration 10 days, should start 20 days before 01 Dec 2019. Task 2, duration 20 days, should start 50 days before 01 Dec 2019, etc.
How can I set this up? I would like to be able to amend the finish date (if needed) and have the dates for all tasks recalculate.