1

I have a project that has multiple workstreams. In much the same way a single task may require multiple people to work on it, it also may touch multiple workstreams.

I created a custom column called workstream with the list of workstreams to choose from but I can only select 1 workstream per task. Is there a way to set it up so I can select multiple workstreams (check boxes rather than just a drop down list)?

1

Using Project Server, you can create enterprise custom fields that allow multiple values to be selected from a drop-down list. But this option is not available in MS Project.

2
  • Thanks so much for the answer. I was pretty sure I looked everywhere but thought I'd ask. At least I know to stop trying now. Appreciate the "closure" :-) – Jodie Smith May 28 '19 at 20:59
  • Glad to help. Speaking of closure, can you mark this answer as accepted? – Rachel Hettinger May 29 '19 at 0:10