I am preparing a high-level project plan in mpp to see the top level view when the project will finish based on the resources availability and work estimation. My requirement is as: I have an estimation of Task 1 for 365 days. Two resources are available from 3 June and three more would join in Oct. I have to see based on the work and resource availability when the project will finish. I added 365 days in the work column, assigned 5 resources and adjust the start date of all 5 resources. But, the mpp has distributed the work evenly across all 5 resources so that first 2 resources would leave the project early and 3 resources joining in Oct work at later date. What I want is all 5 resources would finish the project at same date so it would give me project completion date. Please suggest how to do? Any other method to do without mpp?
Thanks Vibha