Is there a way to show user stories that have no tasks? I need this stats to be shown in a report.

1 Answer 1

1

Using the JQL you can use the issueFunction not in hasSubtasks() combined with issuetype != Sub-task

So the query will look like something like the below:

projectname = [Name] AND (issueFunction not in hasSubtasks() AND issuetype != Sub-task)
2
  • Sorry, forgot to mention "without using plugins".
    – diman82
    Jun 4, 2019 at 15:58
  • Then I recommend using a label to mark the stories with no sub-tasks and filter based on the label.
    – Yassmeen
    Jun 5, 2019 at 9:13