2

In Azure DevOps, under the Scrum template, is there a way to auto calculate the Backlog Item's "Effort" field based on the summation of its child Task items' "Remaining Work" field?

Example:

  1. A new Backlog Item is created. The "Effort" field is left empty.
  2. A new child task for the previous Backlog item is created, the "Remaining Work" field is set as 5.
  3. The "Effort" field of the Backlog Item created in step 1 is automatically updated to 5.
  4. A new child task for the Backlog item defined in step 1 is created, with the "Remaining Work" field set as 3.
  5. The "Effort" field of the Backlog Item created in step 1 is automatically calculated to 8 (the sum of 5 and 3).

How can this be achievable?

If this is not possible, how do you guys manage the correlation between a backlog item's estimated effort and its children tasks' remaining work?

1 Answer 1

2

Jira does do what you ask natively.

You can do what you want with a free plugin VSTS Rollup

https://marketplace.visualstudio.com/items?itemName=canarysautomationspvtltd.vstsrollup

But this is a disfunction in Scrum, your items are far too big. You should not need to do this

From Jeff Sutherland's (co creator of Scrum) latest book on Scrum Patterns:

No Sprint Backlog Item typically should be any larger than a single Development Team member can complete in a single work day.

Sprint items should be as small as possible, if you need to get a tool to sum work for you you are working on an item that is far too complicated and risks failure.

1
  • 1
    You are right. According to this entry in Scrum.org, backlog items should be kept as small as possible, therefore this question reveals a misunderstanding of the concept of a backlog item in Scrum. In conclusion, the final answer should be "you should not have the need for this". Jun 8, 2019 at 19:03

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.