4

Even for smaller projects, some PRINCE2 roles should not be combined. Does anyone know if this is also the case with the roles of Executive and Project Assurance? First of all I'm wondering how this would inlfuence the dynamic with the Project Manager.

1 Answer 1

2
+50

Project Assurance

Project Board's responsibility to assure itself that the project is being conducted correctly. Each member of the Project Board has a specific area of focus for Project Assurance:

  • Business Assurance for the Executive.

  • User Assurance for the Primary User.

  • Supplier Assurance for the Primary Supplier.

Executive

Individual with full responsibility to ensure that the project achieves its objectives and delivers the projected benefits. This individual should ensure that the project maintains its business focus, has clear authority, and that work, including risks, is actively managed. The Executive, in addition to being responsible for the Project Board, representing the client, is also responsible for the Business Case.

Executive vs Project Assurance

The Executive is responsible for the Project Board, which is then responsible for Project Assurance. However, an independent Project Assurance team may also be appointed by the Project Board.

Implications for the Project Manager

To the PM is given the authority and responsibility to manage the project on a day-to-day basis and to deliver the required products within the constraints agreed with the Project Board.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.