0

Picture of problem

I calculated the span based on my start and finish dates to double check the file.

Why are these two columns not equal? Is there a setting wrong somewhere? Does this mean my end date isn't being accurately calculated?

0

The calculated span does not include the time between 3/22/05 5:00 PM and 3/23/05 8:00 AM which would be exactly 62 weeks after the task started (1/14/04 8:00 AM).

Note: MS Project has been around for a long, long time; it calculates the dates correctly.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.