It seems as though I can't set full days and part days in one go?

I've created a new Calendar from the standard calendar and can assign the full days but cannot see how I would split that one day in particular.

1 Answer 1

2

On your new calendar, no exceptions needed. Check [Default] Details on the Work Weeks tab. Make Monday a non-work day, then delete the second shift on Friday. Done.

enter image description here

1
  • In my head, I was over-engineering this! Works perfectly. Thanks. Jun 26, 2019 at 14:39