I'm not sure if a Gantt chart / Gantt software is the wrong tool for my use case, or I'm unaware of some technique / terminology.

Given (1) a set of tasks, (2) time estimated to complete each task, and (3) dependencies to other tasks, I want a view that shows when each task would be completed if a single resource were allocated evenly among all tasks.

Maybe easier to imagine: "Roughly how much can be accomplished by September given a 1-person team?"

So far I've played around with Teamweek and TeamGantt (advanced trial) with no luck. These seem to require manually assigning hours or tasks per day per resource, whereas I want that assignment done automatically, rolling over incomplete tasks (e.g. unexpected sick day) automatically as well, so that I always see a forecast of completion.

Are Gantt charts the wrong tool? Or is there some technique or term I'm missing?

2 Answers 2

1

Ah, I think I found my answer through one of the related questions: Project Management Gantt Tool makes All Tasks Concurrent .

It looks like what I'm trying to do is level resources (in my case, a single resource).

It's not available in TeamGantt for sure, and I don't believe in TeamWeek either.

As of June 29th, 2018, one of the commenters in that link states,

I tested more than 30 project management software and [only] found [resource leveling] in Gantter and MS Project.


Edit

Much easier to research now that I've found the term "resource leveling."

Wrike supposedly supports resource-leveling as "Workloads", but it costs over $65/month to get Gantt charts (for 5 users), and then more to get the Resource integration that introduces Workloads. Microsoft Project, in comparison, currently costs $30/month/user. So, I guess it depends.

0

If I understand your problem properly:

I think you would get the result you expect if you treat your resource as a task - I think most software would then handle it properly.

1
  • Could you say a little more? I'm sorry but I don't understand. Jul 1, 2019 at 23:13

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.