Having some issues with Microsoft Project. Making a task marked as complete (100%) whatever the view, the task gets set to have a Start/Finish (including the Actual Start/Finish) date to that of the Project's Start date, regardless of the task's Sprint date, the Current Date (set in Project Info), or the Status Date (set in Project Info or stand-alone).

Ultimately I'd like to use their agile functions so it'll update correctly when a task is moved to In Progress and then to Complete, but I'm running into the same problem whether in the Gantt Chart or Task Board view, so it seems systemic.

Any ideas for how to resolve this? Can't figure out why this would be the case but I'm likely missing something.