0

The Fibonacci sequence is to assist developers with project estimates. The concern is that we consistently see management use the points derived from Fibonacci sequence estimates to determine project velocity, or more importantly - developer efficiency. Which makes obvious sense to do considering that the point of any given project estimate methodology is to, well, estimate the velocity and remark on the trends.

The problem here becomes evident when you consider that a developer could easily demonstrate in one two-week sprint that they crushed 16 points worth of 1-to-2 point backlogs/tasks and then reasonably take two sprints on a single 8-point task. Now that developer has to defend herself as to why her velocity has dropped 400%.

Well she should get better at project estimates.

That's irrelevant. Considering the whole point of the Fibonacci scale is to provide some sense of exponential effort between tasks, a 1-point task vs an 8-point tasks is an 800% difference. In the case above, the developer actually underestimated but management quantitatively sees a dip in performance.

Then the team needs to define what the different points mean.

The only concrete definition a team could come to a consensus on is how much time a 1-point tasks takes vs an 8-point task but if we start trying to put time frames on it, we're defeating the purpose of this agile project estimate methodology; we might as well refer back to flat time estimates.

Well then management needs to understand that the points are exponential and that 16 points achieved in one sprint compared to 8 points in another sprint doesn't necessarily mean velocity went down.

Then why are we going through the trouble of measuring velocity if it's so relative anyways? If we're going to make management understand the complexity of each task that happened in the sprints, then why even use a point system that is consistently used to measure velocity? To be safe, why wont developers start overestimating their points so they cash in more points per sprint? All of these what-ifs and "it depends" doesn't sound very agile.

  • 4
    Developers don’t have velocity. Teams do, and it’s supposed to be a planning tool rather than a productivity metric. Using it to measure individual performance is Doing Story Points and Agile Leadership Wrong™. – Todd A. Jacobs Aug 29 '19 at 23:30
  • @ToddA.Jacobs So it's not supposed to be a way for management to hold a team accountable for their efficiency? – 8protons Aug 29 '19 at 23:38
  • 3
    Correct. Treating it as a performance metric is a known anti-pattern. Its actual purpose is primarily to help the team avoid over-committing during Sprint Planning, and as an early-warning system to draw attention to hidden blockers. – Todd A. Jacobs Aug 30 '19 at 0:46
  • 1
    "Considering the whole point of the Fibonacci scale is to provide some sense of exponential effort between tasks" That is not the point of the Fibonacci scale, because that can also be seen in continuous-scale hour estimations. The point of the Fibonacci scale is in the increasing gaps between the numbers: As work packages grow larger, their estimates become less accurate. A 13-point story is estimated to take between 8 and 20 times as much effort as a 1-point story, as there are no other values within that range. – Bart van Ingen Schenau Aug 30 '19 at 7:41
3

Velocity was never intended as a performance measure. It is designed specifically to help teams to estimate their capacity in future sprints. If it is being used to criticise the performance of teams then you have a problem.

What this highlights is not that there is an issue with the Fibonacci scale, but how important it is that everyone involved is educated about the agile approach that is being used.

Agile has never been just about the development teams. It is something that the whole organisation needs to understand and adapt to.

1

Now that developer has to defend herself as to why her velocity has dropped 400%.

If the developer is having to defend velocity changes on sprint by sprint stats alone, that is completely wrong. The team will know if someone isn't putting in the effort needed.

It might be that a three, or five, sprint rolling average might be a more realistic measure.

However, here's another idea I like to encourage. Points are a rough estimate of complexity, relative to each other. If the team end up with a high points estimate, then it's an indication that the story is probably too big.

If a story get a points estimate that's something like 50% of a sprint's typical velocity, then that should be a flag. If it ends up taking more than 50% of the sprint to develop, then are you actually going to have time to complete it in the sprint if defects are found, or some other blocker emerges?

Therefore, try to break that story down in refinement if it gets that sort of estimate.

However, it's not always the case that this things can be foreseen, perhaps the issues emerge after development has started. I'd always encourage my teams to fail fast here, abandon the story and take that knowledge to the BA to create further stories, don't plough on trying to sort everything out on the first story. Treat the original one as a spike.

Basically, you'll get a good consistent flow of stories, and therefore a pretty regular velocity, when you are always dealing with stories of 1, 2 or 3 points, maybe the odd 5. This should also resolve your last point about the temptation to overstate the points.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.