2

We are using MS project professional.

Question : Assume I have a schedule A. There are 4 developers assigned to A as well. My management asks if they pull 2 resources out what will happen to the schedule.

  1. Can I create an alternative schedule with 2 devs with existing tasks and constraints, estimates and compare with original schedule to understand the impact ? (Not a baseline)
  2. Can you use a revisioning in MS project. For example I go ahead and create new schedule with 2 devs and call it revision 2. Once I understand the impact can I revert back to original revision ?
1

Make a copy of the original schedule by doing Save As. Then change the number of resources, let it calculate and save the new schedule (Rev 2). Use the built-in Compare Projects feature to compare the two schedules (Report tab).

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.