0

Does anyone have any idea or could provide me with any insight about how to setup S-Curve graph based on "% complete" column ? This would be very helpful as I am stuck with this task for 2 days.

Thanks.

2
  • Hi KhalilG, welcome! Asking for links is off-topic (falls under software recommendations), but the question itself is ok. Feel free to make the right adjustments. Dec 17 '19 at 12:56
  • Did you try using the burndown report?
    – Jens
    Dec 17 '19 at 14:50
1

Under the tab [Report], you can select the [Burndown] report. This report shows the amount of open and completed tasks. You can also include the "% Complete" line in the graph. Example of a burndown graph