0

Does anyone have any idea or could provide me with any insight about how to setup S-Curve graph based on "% complete" column ? This would be very helpful as I am stuck with this task for 2 days.

Thanks.

  • Hi KhalilG, welcome! Asking for links is off-topic (falls under software recommendations), but the question itself is ok. Feel free to make the right adjustments. – Tiago Martins Peres 李大仁 Dec 17 '19 at 12:56
  • Did you try using the burndown report? – Jens Dec 17 '19 at 14:50
1

Under the tab [Report], you can select the [Burndown] report. This report shows the amount of open and completed tasks. You can also include the "% Complete" line in the graph. Example of a burndown graph

| improve this answer | |

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.