For a support project the sprints contains defects and hardly any enhancements, does sprint goal or increment still be applicable?
For e.g. my upcoming sprint has 3 defects:
Defect 1 : Screen flickers on mouseover.
Defect 2 : Save button click not working.
Defect 3 : Report generation takes more than 30 minute for large set of records.
In this case what is my increment
? What is my sprint goal
?
The reason for the ask is, (as per guide) if the Development Team realizes that selected work will exceed the timebox of Sprint they have to collaborate with Product Owner to remove some work but they need to fulfill the below rules which for me doesn't makes sense:
No changes are made that would endanger the Sprint Goal;
Quality goals do not decrease;
Scope may be clarified and re-negotiated between the Product Owner and Development Team as more is learned.
Not sure but I hope my question makes sense.