As far as I understand, in Kanban, each column is divided into two sub-columns: "In Progress" and "Done". A performer from the next column pulls the items from the previous column's "Done" sub-column. This is how a pull system works.

But in Jira's Kanban board there is no way to divide a column into "In Progress" and "Done". How do you cope with this?

Does this limitation forces team members to always ask the other team members (from the previous column) which of their items are "Done"?

  • When talking about Jira, questions and answers should consider that every project uses a specific set of default workflows and columns. Do not assume that the ones you have are the ones other people has. Assume there's no default. – Tiago Cardoso Jan 8 at 11:27
  • Besides, is there any link or external reference that explains what you meant by "sub-columns"? I never heard about this concept. – Tiago Cardoso Jan 8 at 13:37
  • This needs more context. Why do you think JIRA can’t add columns? And why do you think post-task queuing between columns will improve flow? – Todd A. Jacobs Jan 8 at 13:43
  • @TiagoCardoso i think what ChrisBrettini means with sub-columns are, in fact, the status of each column and, therefore, why I answered the way i did. In his specific case, it seems he has organized each column with status "In Progress" and "Done". – Tiago Martins Peres 李大仁 Jan 8 at 15:15
  • 1
    Got your point @TiagoMartinsPeres - you're right. I had never seeing statuses being called sub-columns. – Tiago Cardoso Jan 8 at 17:22
2

JIRA allows you to modify your workflow and add new statuses. You don't need to divide columns, just add new columns that reflect what you want.

I would look to build a workflow something like this:

To Do

Dev

Dev Done

Test

Done

Thus a tester would look at the "Dev Done" column for work that they can pull into "Test".

If you have more elements in your workflow you can add the additional 'Done' stages for them as well.

|improve this answer|||||
1

In Jira, the default columns on a Kanban board are Backlog, Selected for Development (To Do), In Progress, and Done.

For each column, depending on the workflow you're using, you have different status.

If your board's project is using the Jira default workflow:

  • To Do - Open, Reopened
  • In Progress - In Progress
  • Done - Resolved, Closed

You can change the workflow or delete / add / edit the status if you want to.

|improve this answer|||||
  • 1
    Yes, just change the default Jira workflow and/or board layout to meet your specific needs. – robbpriestley Jan 7 at 14:49