0

I have a task (row 100) which have two predecessors, row 20 and row 30. As it is now, row 100 starts 4 weeks after row 20 has finished and 4 weeks after row 30 has finished. Is it possible for MS Project to automatically schedule after which one of the two tasks that finishes last. So for example if row 30 is delayed with two weeks, I want row 100 to be rescheduled so it still starts 4 weeks after row 30 has finished (and now 6 weeks after row 20 has finished). How do I do this in MS Project?

1
  • 1
    What happens if you list the predecessors of task 100 as 20,30 +28d?
    – MCW
    Jan 21, 2020 at 13:49

1 Answer 1

1

Yes. On task 100 you would add both task 20 and task 30 as predecessors, with a finish-to-start relationship and 20 days (4 weeks) of lag. Once added, the earliest task 100 will start is 4 weeks after the latest finish of tasks 20 and 30.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.