3

Can two different roles be responsible for the same task in the RACI matrix?

If Yes, how do you ensure that there will be no conflict between those two roles when it comes to actual task delivery?

If No, does it mean that the matrix is inadequate when it comes to assigning responsibilities to the appropriate roles?

1 Answer 1

0

There is an expanded version to RACI called "RASCI" - the "s" stands for "support".

The support takes an active part in working on the task.

Responsible

Those responsible for the task, who ensure that it is done as per the approver

Support

Resources allocated to responsible. Unlike consulted, who may provide input to the task, support helps complete the task.

See: https://lifehacker.com/use-the-rasci-matrix-to-manage-responsibility-on-a-proj-1753137259

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.