I am using MS Project to get Schedule Variance of a project. At this point in time I have put all the tasks associated with the project, assigned resources to the tasks (all of the resources are type 'Cost'), and create it a baseline for the entire project. If I am not mistaken, I should start tracking the progress of the proyect so MS Project can start doing its Earn Value calculations.
One of the task should have last 19 days and cost $2,500 to complete, instead it took 25 days to be completed but with the same cost. Looking at the list of dependencies I see that this particular task is not associated with any of the other task.
Here is where I don't understand what is going on: Checking the EV tables I see SV equals 0, I would think SV should be equal to a negative value, which indicates the project is behind schedule, no?