How exactly does MS Project calculate Peak Units?
Let me explain the situation: I have a task named 'Task 2', it has a duration of 2 days, 20 hrs work, Fixed Duration, from Monday to Friday a resource works 11 hrs, and 9 hrs on weekends (I changed the default working time from 8am to 5pm, to 7am to 7pm through 'Change Working Time').
I also have a Resource named 'Mike', his Max Units is 100%, he is assigned to Task 2, his assignment units is equal to 100%; If I remember correctly that means that his working 11 hours each day on the task.
MS Project assigned Mike 12.5 hrs on Thursday and 7.5 hrs on Friday, Task Usage reports a 114% percent allocation for Thursday & 68% on Friday; both of the percent values makes senses.
What I don't get is how is MS project reporting a Peak value of 125%? Should it not be equal to 114%?