Can somebody help me with below. I am trying to get the correct numbers on the task Name Test Project. I would expect to see 24 hours on the duration. This only works when I use predecessors, which is weird as both task have a different resource so they can work on different tasks at the same time.
Task calendar of resources and task is Standard Different resource per task Not sure if it's related but I found the field Rollup and changed it to YES for all
Not working!
Working! but I do not want to use predecessors