My need would be to have a team view macro planning in relation to the workload of each subject.

Microsoft project works by resource and not by team.

How can I model this global capacity per 3-week view in Microsoft project?

Weeks | Period | Capacity/MD

W18-19-20 |27 April -> 17 May |58.5

W21-22-23 |18 May -> 07 June |63,75

W24-25-26 |8 June -> 28 June |67,5

W27-28-29 |29 June -> 19 July |66,75

Then I would like to associate subjects to it in order to obtain their realization in time.

If there are other tools that address this issue, I am open to learning about them. Thank you very much.