I have a project KPI that I can measure daily: the use of a bottleneck resource, measured as the % against a target value of hours of use.
Example:
- Week_1
- day_1: 100%
- day_2: 95%
- day_3: 95%
- day_4: 95%
- day_5: 95%
- Week_2
- day_1: 100%
- day_2: 100%
- day_3: 100%
- day_4: 10%
- day_5: 10%
The goal for this KPI is to accomplish 100% of use on a daily basis.
Week_1 was not very successful (1/5) in terms of "complete accomplishment of 100% use", but each day was very close to the 100% goal.
Week_2 was somehow successful (3/5) in terms of "complete accomplishment of 100% use", but the bad days were very far from the goal.
Now I want to summarize the week with one single metric, and I want it to be fair and informative.
If the weekly summary metric is something like the number of days when the 100% goal was accomplished (1/5=20% and 3/5=60% in the previous examples), I don't know if it is fair, but it is not very informative.
If the weekly summary metric is the average of the daily scores (96% for Week_1 and 64% for Week_2 in the previous examples), it is probably not fair and not informative.
What would be the best way to build a metric to summarize the week?