How can I add a new filter that allows me to select tasks without a filled "estimate" field. I read about the ability to save search results as a new filter - but that doesn't work. I need to be able to filter by the "estimate" field, if it is not filled.
-
1Hi - you're looking for a JQL filter like remainingEstimate is empty. With that said, I believe this question is way too specific on Jira to fix the pm.se guidelines. More details on help center. – Tiago Cardoso♦ Jun 2 '20 at 11:26
project = myProject and estimate is EMPTY
Where myProject is either the key prefix for your tickets (EX: JIRA or ABC etc) or myProject is the actual name of your project
And where estimate depends on what you use, story points, time logging, etc
We use time logging, so my JQL search would like this
project = "Legacy" and originalEstimate is EMPTY
If you are estimating using story points, filter would be something like
project = PROJECT_NAME AND "Story Points" = 0 ORDER BY created DESC
You can omit Project = PROJECT_NAME as well. You can anyways replace story points field with whatever the estimate field you are using.