1

I'm using MS Project which is connected to a PWA. All users complete their tasks on the online 'Tasks' page. For the task owners, I need a flag that tells them that all the predecessors for their task is complete. I can see how to do this in VBA with the following code:

Sub GetPredStatus()
Dim pj As Project
Dim t As Task 'subject task
Dim p As Task 'Predecessor task
Set pj = ActiveProject

For Each t In ActiveProject.Tasks
    If t Is Nothing Then GoTo NextTask

    For Each p In t.PredecessorTasks
        If p.PercentComplete < 100 Then
            t.Flag7 = False
            GoTo NextTask
        End If
    Next p
t.Flag7 = True
NextTask:
Next t
End Sub

The problem is, I need this flag to be 'live' and accurate to task users in the PWA. Is this possible?

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Browse other questions tagged or ask your own question.