2

In my company, I am constantly struggling with how to accurately communicate the priorities of tasks. Some of the aspects of this are:

  • Some tasks need to be done before a deadline, however, sometimes they will no value one second after the deadline, while others need to be completed as fast as possible after the deadline.
  • Some tasks have the highest priority if their ROI (return on investment) is high, however, if the ROI estimates change, then they will lose priority. So for example a project that was supposed to cost 1,000 and save 2,000, should maybe loose priority after having gotten delayed and we have already spent 3,000 on it.
  • If one sets a deadline on a task, it should maybe still have a priority (possibly communicated in points), so that a task will never become more important than saving a life (just the most extreme example), even though there is just one second left until its deadline.
  • If a task is dependent upon another task, which has gotten delayed, then the task should loose priority until the task it is dependent upon is on schedule
  • If one is building a building where everyone in the building project is waiting for a crane to be set up, then looking for one missing screw for the crane might become the top priority for 100 building people, even the CEO.

Today, I fall back to very crude ways of communicating priorities, by for example saying that a task or a project has "medium" priority. Or by setting deadlines. So what I am looking for is inspiration for communicating better. The communication could be done with the help of software, which constantly calculates the priority (this is a way of communicating), or by introducing new terms like "deadline, with 0 value 1 second after deadline" or whatever.

  • Just out of curiosity, in what field/domain do you work? – Bogdan Jul 22 '20 at 15:35
  • @Bogdan My field of work is as the CEO of a company developing accounting systems and performing accounting services, but also consultancy typically for management of hospitals. – David Jul 23 '20 at 9:30
4

Good question. I'm unclear on some of the details that inspire your question, so I'm going to provide three different answers

Risk Matrices are dangerous to your health.

You say,

I fall back to very crude ways of communicating priorities, by for example saying that a task or a project has "medium" priority.

Tony Cox and others have done some persuasive research that "medium" is a recipe for failure. Brief summary is that "medium" is a term without units, and gets interpreted inconsistently by all parties in the discussion, leading to misunderstanding. Cox et. al. recommend communicating risk through value - $ of dollars or time at stake. You're looking for "this screw costs $0.02, but failure to have this screw in the parts inventory risks a set of delays that will set the project back 3 months and cost $15K +/- 3K."

Risk Breakdown Structure

There are many ways to build a Risk Breakdown Structure; I'll describe briefly one way that I do it in my current work. I use a synthetic number which is derived from the risk and the suspense.

  • Risk measures the impact on overall project if the task fails to meet the scheduled deadline. You'll have to do your own risk calibration; mine would be useless to you. You need to set a clear scale from low/"nice to have" to high "life threatening". It isn't completely clear from your example, but I think you're actually working from a value at risk model.

  • Suspense date is set for each task, and is the date at which the risk needs to be recalculated. I measure in days because that works for my project.

For every task I calculate the risk/time to suspense. (I actually include the amount of work remaining, but that isn't relevant to the question you ask.) That number tells me what I need to worry about today. I can then break it down to an "Eisenhower matrix" style communication, "This task must complete or update within 10 days and failure will put $x thousand dollars of work at risk. How confident are you that the work will be complete by date Y? What could go wrong? What are the potential blockers and how can I remove them? "

Referencing your cases:

  1. (Task must be done before deadline) is Urgent/time sensitive; the risk derives from that deadline
  2. (Task ceases to be important after deadline) - Prior to the suspense date the risk (value at risk) is high. After the suspense date drop the value at risk to negligible.
  3. (case is unclear) - I think this is resolved by treating the value at risk separate from the time risk. Some tasks are urgent (resolve within 3 days or else abandon), some tasks are important (I have a year to solve this, but if I fail, it will cost a life).
  4. (task depends on task that has slipped). I don't deal with a lot of coupled dependencies. If I had this situation, I'd include "downstream risk" in the risk number. I'd add the risk of all dependent tasks to the risk value.

Don't communicate risk; communicate options

In general, I avoid discussing risk. I've found that managers stop listening when I do. What I communicate is options and ownership.

Internally I generate the list of risks, rank order them from highest to lowest. I then establish a cutoff and work the issues that are above that cutoff threshold. What goes to management is a watchlist - an ordered list of worries.

  1. Task X depends on a $0.02 screw, but the screw is rare. I've called the supplier and asked them to confirm that the screw will be available, but it would help if you'd call and reinforce the message - let them know that if we don't get that screw on time, it will cost us $15K. Remind them that we're planning on buying $X from them next year, and we'd like a good relationship.

  2. Task Y will hit a critical milestone in the next 5 days; if we slip this milestone it is likely that tasks W, K, and L will slip as well. Robin in HR is responsible for the action. Robin says that so long as she can concentrate on task Y, the task will complete on schedule, but Robin needs to concentrate on task Y with no distractions. Can you help assure Robin?

  3. Task Z is on my watch list because $20K of other work depends on it. We're going to have to make a decision on how to proceed within the month. Avery says that the decision memo has been sitting on Jordan's desk for 5 days. If that decision memo isn't signed by the 20th, the work will be delayed by a week, and every week will cost 3K. Can you call Jordan and communicate the importance to our project? Jordan's office tells me that the delay is because the decision will impact Charlie's project, so you may wish to discuss it with Charlie first.

And so on - those aren't risks, there are no "mediums" - there are just lists of consequences and options.

  • 1
    Don't communicate risk; communicate options --> I like! – KargWare Aug 31 '20 at 10:49
2

Ideally priorities shouldn't change frequently - it's much easier to work in a stable environment and not have to switch between tasks and priorities quickly. The reasons for frequent changes could be:

  • Hectic managers and/or stakeholders - they panic and change their mind all the time
  • System constraint not defined. If you don't know your slowest/most fragile part of the process - you can mistakenly redirect resources from it. Shortly after that this will slow down the whole system.
  • Low quality of the product or environment - something keeps breaking and we keep fixing
  • Business model is built around screwing someone over instead of doing a good thing together with them

If one of those is true for you - try to fix it.

But if it's really not fixable, if it's the type of work that you do that's so unpredictable (could you describe it in more details?) then coordinating tasks is a full time job. You probably need a person who's always available, who can always tell to do this task and not the other.

  • The main cause of changing priorities in my case are: - Difficulty in estimating the cost of a project before starting the project (typical IT development) - Difficulty in resource-planning because we are too small to have many dedicated resources and because we have an operation that needs to have higher priority than development projects. - And surely, I am a hectic manager, which is why I want to be better at delegating, which means that I need to delegate in ways where I communicate the priorities clearly. – David Jul 23 '20 at 9:39
  • @David probably estimating the costs incorrectly is the most pressing issue. If the business model can be changed from Fixed Price to monthly payments, and if stakeholders see the progress and don't insist on long-time commitments - this would most likely fix a lot of problems. Some people also like giving promises - that's a bad habit too because then you're morally obliged to deliver in time. "We'll notify you once it's done in about 3-5 months" is a safer model :) – Stanislav Bashkyrtsev Jul 23 '20 at 11:23

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.