0

How do I create a task in Microsoft Project Pro 2019 that takes 1 person 8h to complete. I don't care about the duration or anything else, only that there are 8h spent working on the task. Normal working hours in the project are 8h/day.

  • If I add a resource working 100% in the project, the duration should be set to 8h
  • If I add a resource working 50% in the project,then the duration should be set to 16h.
  • Optional: If possible, I want to limit the task to max 1 person at a time (i.e. the task is about nailing and we only have one hammer).

1 Answer 1

1
  1. Create the task with type = Fixed Work. (You can set the task type on the Task Form-in the lower pane, on the advanced tab of the Task Information dialog that opens when you double-click the task, or by inserting the "type" column into the task table and making the entry there.)
  2. Set Work = 8h
  3. Assign your resource at whatever percentage you want (Using the Task Form or the TI dialog). The task duration will adjust automatically.
1
  • Setting the task to be Fixed Work is not a problem, but the only TimeSpan field that's available in the Task Form or the Task Information dialog is Duration. Sep 10, 2020 at 17:24

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.