How do I create a task in Microsoft Project Pro 2019 that takes 1 person 8h to complete. I don't care about the duration or anything else, only that there are 8h spent working on the task. Normal working hours in the project are 8h/day.
- If I add a resource working 100% in the project, the duration should be set to 8h
- If I add a resource working 50% in the project,then the duration should be set to 16h.
- Optional: If possible, I want to limit the task to max 1 person at a time (i.e. the task is about nailing and we only have one hammer).