When I update MS Project for the current date, the program is generating start constraints on activities that have not started yet. These activities do not need to start at the update Date, but can start later based on the logic and available Slack.
Why is it creating a start constraint and not allowing the activity to move forward to the current date if it has not started? How do I get the program to stop creating "constraints"?