How do you highlight this line? It's hard to see in "stock" format.
Two options. You can either zoom in by right clicking the chart and selecting zoom, or you can do a right click on blank space in the gantt chart, then choose "gridlines", then highlight the "current date" and select the line colour.
Right-click on a blank space on your Gantt chart, choose "grids ...", highlight "current date," and set the color and line type.
-
Hi sonnu, welcome! This answer is the same as TimmyTurner9's answer which is already marked as accepted. This means that this is not a good contribution. The only way I can think to save this answer is by editing it and including screenshots of the process. That way it'd bring something new to the table. – Tiago Martins Peres 李大仁 Nov 24 '20 at 6:31