Microsoft Project--- In our project calendar we have changed working time from 8 hours to 9 hours all times are correctly set 8 to 12 and 1 to 6 for monday to friday

but after changing default end time in ms project options it doest change end time from 5pm to 6 pm, rather it changes the duration and thus when i assign resource, work is 8 hours

so is there any way to change end time of all existing tasks when i change default end time so that assigned resourses work will also be changed from 8 hours to 9

Note: these changes are being done on existing projects, all task are auto scheduled New projects are working as expected