I am running a report and it would be great to identify the summary task of a task - is this possible?
Reporting via the project API.
E.g. I have the following schedule
WBS | Task | Resource | Custom Field | Summary | Start | End |
---|---|---|---|---|---|---|
1 | Project Initiation Document | Yes | 01/02/2021 | 22/02/2021 | ||
1.1 | Draft | PM | Governance Doc | No | 01/02/2021 | 06/02/2021 |
1.2 | Review | Steering group | Governance Doc | No | 06/02/2021 | 11/02/2021 |
1.3 | Update | PM | Governance Doc | No | 11/02/2021 | 16/02/2021 |
1.4 | Sign-off | Steering group | Governance Doc | No | 16/02/2021 | 21/02/2021 |
1.5 | Publish | PM | Governance Doc | No | 21/02/2021 | 22/02/2021 |
And wish to return the following table via the reporting API
Document | Task | Resource | Start | End | ||
---|---|---|---|---|---|---|
Project Initiation Document | Draft | PM | 01/02/2021 | 06/02/2021 | ||
Project Initiation Document | Review | Steering group | 06/02/2021 | 11/02/2021 | ||
Project Initiation Document | Update | PM | 11/02/2021 | 16/02/2021 | ||
Project Initiation Document | Sign-off | Steering group | 16/02/2021 | 21/02/2021 | ||
Project Initiation Document | Publish | PM | 21/02/2021 | 22/02/2021 | ||