2

0

Probably best described by example:

I have a project with 10 tasks of 1 day to be done by 1 resource. So they have to happen sequentially, easy to arrange by levelling or linking and the project will last 10 days. But this sets a task order, and it seems that Project expects them to be done in that order.

If they are, it is easy to get an indication from the standard reports about overall project progress. I can get a "late tasks" report which will show exactly that.

But the reality in our projects is that each task is done a bit at a time. So after 5 days, we are just as likely to have done 50% of all the tasks, or 100% of the last 5, as 100% of the first five and for us, that is equally satisfactory progress.

I have tried but I can't seem to find a way of knowing if the overall project is on track by work done regardless of task order. Is there an easy answer for this?

2 Answers 2

2

This can be handled by treating the tasks as though they all start on the same day and run for the full 10 day duration, while allocating the same resource at 10% availability to each task.

This is very similar to the following question: MS Project: Multiple tasks for one employee

There is also some information on this here: https://www.mpug.com/hidden-functions-in-projects-assign-resources-window/

2
  • This is how I would resolve this problem. Great answer. Feb 8, 2021 at 18:48
  • 1
    Thanks @DavidEspina - I struggle to describe how to do these things as I don't have a copy of MS Project on my pc any more, having retired from work, but at least the old grey cells still know what to do!
    – Iain9688
    Feb 8, 2021 at 19:08
1

If they can be done in any order, by a single resource, it is a single task

Welcome to pm.stackexchange!

If these can be done in any order, I will keep these as a single task of 10 days duration and assign it to that single resource.

after 5 days, we are just as likely to have done 50% of all the tasks, or 100% of the last 5, as 100% of the first five and for us, that is equally satisfactory progress.

After 5 days, any of the above combinations will show that task as 50% complete. I think you are unnecessarily adding complexity by splitting that into 10 tasks.

1
  • I think this is also a reasonable solution to this problem. The more detailed ten tasks can be documented in the WBS Dictionary and Def of Completion. But if there is a need to capture actual costs of the ten detailed tasks, such as if there was a color of money issue, then @Iain9688's solution will work. Both great answers. Feb 9, 2021 at 21:28

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge that you have read and understand our privacy policy and code of conduct.

Not the answer you're looking for? Browse other questions tagged or ask your own question.