I have a project that I have 15 main tasks on. One of them is Meetings
. I have had X
meetings, and the duration is 1-day
. Is there any way to show multiple bars on a single line showing these Meetings as square bars? (something similar that the Office Timeline add-in shows/creates in Power Point)
2 Answers
Unfortunately ProjectLibre doesn't support recurring tasks
Welcome to pm.stackexchange!
Is there any way to show multiple bars on a single line showing these Meetings as square bars?
In order to show multiple bars on a single line, you need to be able to create recurring tasks. Unfortunately ProjectLibre doesn't have the capability to designate a task as 'recurring'. So, the answer is, no you can't do that.
You can check the documentation here - ProjectLibre User Guide v1.3.0 Aug 2020.
-
Thank you. Would you know if MSO Visio supports this? If so, which versions? Commented Feb 9, 2021 at 8:33
You can split a task by right clicking and selecting split. If you combine this with displaying as a milestone you can place diamonds where each meeting is required.