1

I have a project that I have 15 main tasks on. One of them is Meetings. I have had X meetings, and the duration is 1-day. Is there any way to show multiple bars on a single line showing these Meetings as square bars? (something similar that the Office Timeline add-in shows/creates in Power Point)

1

Unfortunately ProjectLibre doesn't support recurring tasks

Welcome to pm.stackexchange!

Is there any way to show multiple bars on a single line showing these Meetings as square bars?

In order to show multiple bars on a single line, you need to be able to create recurring tasks. Unfortunately ProjectLibre doesn't have the capability to designate a task as 'recurring'. So, the answer is, no you can't do that.

You can check the documentation here - ProjectLibre User Guide v1.3.0 Aug 2020.

1
  • Thank you. Would you know if MSO Visio supports this? If so, which versions? Feb 9 at 8:33

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.