I am using Jira Structure with Gantt and trying to schedule tickets on the project with resource levelling. Instead of levelling one-by-one, it places first a ticket from the end of a structure, then some random ticket from the middle, etc.

Level priority is the same for all issues.

Levelling priority in Gantt config is "Store in Gantt chart". And I have no option there to change it on a Rank or Index (no such things in the dropdown).

So, my questions are:

  1. What I am doing wrong?
  2. How to add Structure index in Levelling priority? (I suppose it can solve the problem)