I would like to create a weekly deployment schedule for components, which would then be illustrated on a GANT diagram.

I would like to create a schedule for the deployment of components by week, which will be shown on a GANT chart. MS Project now allows you to enter a start date and an end date, instead of entering dates, I would like to enter week numbers and at the same time be able to display it on Gant.

For example :

Task A: Start week W4 - End week W6

Task B: Start week W12 - End week W13

Is this possible and if so how can I proceed?

enter image description here

As you can see in the picture, on the right, the gant is well displayed. However on the left side, the purpose is to enter a number of week as a start date, and as you can see I need to select a specific date rather than a number of week.

Thank you

3
  • Are you comfortable with coding in VBA? That's likely the only way to build what you need.
    – Tiago Cardoso
    Apr 12 at 16:20
  • I m not comfortable with VBA, do you know where I can find some macro VBA to help me to do it ?
    – Kikou
    Apr 13 at 5:20
  • 1
    Actually, as Ashok has kindly shared with us in the "answer" below, you probably don't have to use VBA to get this particular job done. However – Kikou, "definitely set aside some time to cursorily familiarize yourself with VBA." There's tons of material out there on the Internet (of course), and it's really not too hard to acquire enough of a working knowledge of it to be really helpful when you do need it. A very short(!) function is sometimes "just what the doctor ordered." Apr 14 at 17:07
2
+50

Here is a thread in Microsoft Technet Forums for Project Standard and Professional General Questions and Answers:

There are two suggestions:

  1. In the options/general menu, select "W04-4" in the date format. Then the start and finish dates will be displayed with the week number and day of the week.

  2. You could also create a custom field with a formula using the ProjDateConv function with the pjDate_Www_dd format option. Doing this, you'll keep the default start and finish date as is and just display week number in the calculated field. Exact formula below:

    ProjDateConv([Start];pjDate_Www_dd)