I'm practicing with PMP quiz and I have this doubt about stakeholder engagement. During a project you can have two main situations:

1 - A change about the stakeholder involved in your project: for example, one stakeholder changes jobs, and you get another one at his place.

2 - A change about the engagement level of one or more of your stakeholders.

in Case 1) you have to change you stakeholder engagement plan.
in case 2) you have to update the Stakeholder engagement assessment matrix

Is this correct?

There is some other case that I have forgotten?

Thanks.