0

How do I add people to a task to reduce the duration of a task? I have a automatically scheduled task that takes 15 days to complete with one person assigned when i try to add people it doesn't reduce the time it takes to complete the task. I am not good with MS Project and need to do this to complete an assessment for college but I can't figure it out.

1 Answer 1

1

You need to select "fixed work" instead of "fixed duration." You can find that functionality in the Task Information area. When you have fixed work selected, and you add a resource, that will change the duration. If you have fixed duration selected and you add resources, it will reduce resource utilization percentage.

4
  • It won't let me change the task type, it's highlighted gray
    – user45237
    Jun 21, 2021 at 13:26
  • Hmm, I'm not sure the issue. You are opening the leaf / lowest task to change its type? There are some really good project experts on this exchange so hopefully they will jump in with a better answer. Jun 21, 2021 at 13:42
  • 1
    Ah I wasn't selecting opening that I have sorted it now thank you very much for your help it is really appreciated :)
    – user45237
    Jun 21, 2021 at 13:52
  • @user45237 Glad this answered your question--don't forget to mark the answer as accepted. Jun 21, 2021 at 14:30

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge that you have read and understand our privacy policy and code of conduct.

Not the answer you're looking for? Browse other questions tagged or ask your own question.