I'm creating my project in Microsoft Project.
What is important to me is who is accountable for a task. For instance, there are 3 tasks that I'm 100% accountable for; 2 tasks that myself and my colleague are 50% responsible.
If I assign accountable people as resources it doesn't work as I expected. Let me explain:
There are 3 tasks for me and I have to finish them within 2 days so all have same start and finish dates. They take not more than 2 hours to execute. If I assign myself as the resource of them with 100% unit, I get "This task has overallocated resources" warning.
In real world people work on several tasks per day.
I've looked into all fields and didn't find anything.
How to implement that?