Is there any way to determine an estimated project date by number of resources allocated? I have set up all my tasks to automatic and effort driven and identified critical tasks and dependencies, but there doesn't seem to be any way to figure out what my projected date is based on whether I have 1, 2, 3 or 4 workers for example (estimated, so spread evenly through the project).
I might have two tasks in the same milestones that if they were done by a single person would have to be arranged sequentially, but if two people could do them, then they can be parallelised. It would be good to find out how many resources I can assign to a project to give the shortest timeline.
I have tried just assigning one resource to every task and levelling the project but this is deemed an overallocation that Project can't solve.