I'm aware that MS Project does not allow you to have multiple instances of the application open unlike the rest of MS Office. I know that you can view multiple projects at once by clicking the Arrange All button in Window group of the View Tab

Arrange All

When I click the button, it stacks the project files on top of each other like this:

Stacked

However, I want the button to arrange them side-by-side, like this:

side-by-side

I can't seem to find a way to do this automatically. I always need to resize and reposition the windows manually. What setting do I need to change to make this happen? I've tried clicking the arrange all button twice, but it does not change the orientation of the windows. I know it's possible because I've seen other MS Project users do it. I'm using MS Project Professional 2016.

2

Doing a quick search I see many people have asked this same question but no answers posted. However, it can be done with a simple macro:

Public Sub ArrangeVertically()

    WindowArrangeAll
    Windows(1).WindowState = pjMaximized
    Windows(2).WindowState = pjMaximized
    
    Dim w As Double
    w = Windows(2).Width
    Dim h As Double
    h = Windows(2).Height
    
    WindowArrangeAll
    
    Windows(1).Width = w / 2
    Windows(2).Width = w / 2
    
    Windows(2).Left = w / 2
    
    Windows(1).Top = 0
    Windows(2).Top = 0
    
    Windows(1).Height = h
    Windows(2).Height = h
    
End Sub

Modify the code as desired to handle cases where the window count <> 2.

1
  • 1
    Thanks Rachel. My current theory is that this feature is inherent in MS Project 2019 and above. I downloaded 2019 Professional and it works out of the box now. I will use this script for versions earlier than 2019. Nov 23 '21 at 20:11

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.