0

Here is my question: I have a go/no-go meeting on the calendar for go-live. We always do go lives on Tuesday. I want to dynamically link the date to always pick the next Tuesday after the go-live. Is that possible?

I can see how to do it manually with a constraint, but if the go/no-go meeting moves up a week or back a week I have to go back in and make changes

1
  • I don't use Project a lot, but won't a one week finish-to-start constraint from go-live do it for you?
    – Todd A. Jacobs
    Jan 25 at 17:10

1 Answer 1

0

I would recommend this:

  1. Create a custom calendar that only has Tuesdays as working days
  2. Create a 1 day task in the schedule called "Go Live Start" or something and set it's Task Calendar to the calendar you created. Make it's predecessor the Go/No Go Meeting. Do not load resource assignments onto this task, it's strictly being created to achieve the mechanics of what you want to happen in the schedule. I would say just make this a milestone but milestones don't honor the task calendar set so you have to give it some duration.
  3. Tie your actual discrete Go Live tasks Start-To-Start with the "Go Live Start" task.

Now no matter where your Go/No Go Meeting is moved to, your Go Live work will always begin on the following Tuesday.

enter image description here

2
  • Thank you Kenny. That worked like a dream! Jan 25 at 18:42
  • One other recommendation, give the "Go Live Start" task some successor like the program end or something so if the schedule is audited the auditors won't make a stink about tasks missing successors. Jan 25 at 22:26

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge that you have read and understand our privacy policy and code of conduct.

Not the answer you're looking for? Browse other questions tagged or ask your own question.