I am trying to make changes to ms project file. I added tasks to wbs for new config and assigned resources enter image description here

And then saved this to Baseline 1.

enter image description here

And then, even changed the baseline under advanced options –

enter image description here

But still the BAC, does not get updated

enter image description here Screenshot from Baseline 1

enter image description here Screenshot from Baseline (original)

Please can someone advise what I am doing wrong?