0

I have the following problem and can not find a solution on google.

ProjDateAdd([Start9];[Duration9];"myCal")

The formula is in the field finish9 and only works if the global calendar "myCal" is used in the current Project. Is there a way to load or use a global calendar with formulas?

Thank you

2
  • Try adding a dummy task that uses the calendar you want so that that global calendar is now available in your schedule. Feb 6 at 15:37
  • Thank you for your Answer. It Works. Feb 7 at 15:23

0

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge that you have read and understand our privacy policy and code of conduct.

Browse other questions tagged or ask your own question.