I have the following problem and can not find a solution on google.

ProjDateAdd([Start9];[Duration9];"myCal")

The formula is in the field finish9 and only works if the global calendar "myCal" is used in the current Project. Is there a way to load or use a global calendar with formulas?

Thank you

2
  • Try adding a dummy task that uses the calendar you want so that that global calendar is now available in your schedule. Feb 6, 2023 at 15:37
  • Thank you for your Answer. It Works. Feb 7, 2023 at 15:23