0

I am struggling to see an option in MS Project when using a custom currency field for the the summary task to total. It shows a zero and I dont know how to change it. See screenshot below. Any help would be great enter image description here

1 Answer 1

0

On the custom Fields screen, be sure to change the Calculation for task and group summary rows to Use formula. enter image description here