I have 4 tasks A-D, each one is a predecessor to the next. My schedule baseline is A->B->C->D. However, tasks A-C order is flexible and doesn't matter which one comes first, they just can't be worked at the same time. Task D has to start once A-C is complete, but as long as all 3 are complete, it doesn't matter if it starts after A or B or C. Once our crew starts the project, the tasks end up being done in a different order (for example B->C->A->D), I have such a hard time updating the schedule because all the links are out of order. I end up having to redo the baseline.
- What's the best way to set up the baseline schedule for these tasks, knowing that I'm going to have to input large changes in dependencies? I'm at a loss.