I am finding the following problem with Microsoft Project.
I defined a task that for example have a duration of 10 days but these 10 days can be spread in a longer time (for example one month) because the involved resources in the meantime are working on other tasks.
My problem is that when I change the end date, Project automatically re-calculate the duration and so I have a bigger number of what I expect. How can I avoid that Project automatically calculate the duration of a task when the end date changes?