3

I have a plan with original dates that I would like to keep but then I have a project phase that is now delayed. Are there recommended approaches when using Project 2007? Thanks

1 Answer 1

1

After an approved change, you can re-plan your next phase and strike a SECOND baseline. You can have multiple baselines in MSProject. Thus you can track your variances to several baselines.

1
  • Pity that project 2007 didn't make baseline management more obvious.
    – SBWorks
    Commented Oct 11, 2011 at 10:47

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.