3

I have a plan with original dates that I would like to keep but then I have a project phase that is now delayed. Are there recommended approaches when using Project 2007? Thanks

1

After an approved change, you can re-plan your next phase and strike a SECOND baseline. You can have multiple baselines in MSProject. Thus you can track your variances to several baselines.

  • Pity that project 2007 didn't make baseline management more obvious. – SBWorks Oct 11 '11 at 10:47