I have a plan with original dates that I would like to keep but then I have a project phase that is now delayed. Are there recommended approaches when using Project 2007? Thanks
After an approved change, you can re-plan your next phase and strike a SECOND baseline. You can have multiple baselines in MSProject. Thus you can track your variances to several baselines.