1

In my company most of the projects are within the same TFS (team system) team-project. Though a more general overview is necessary for execs or cross-application services (IT, DBA and such).

Oh, and we need to see that in MPP Gantt chart. If I'm trying to export to project a multi-project query (i.e. a DBA that takes part in all team projects)- it does not allow.

Can anyone advise/assist?

2
  • Does the software have an export feature where you can get at the raw data?
    – jmort253
    Dec 16, 2011 at 1:21
  • What version of TFS are you using? Also, what process template are you using?
    – JoeGeeky
    Dec 18, 2011 at 19:31

1 Answer 1

2

Unfortunately, it is not possible pull in a query that goes across multiple team projects into MS Project with TFS today.

One workaround -- is to create a project plan and then add sub-project plans (the individual plans that are connected to the team projects) and form a "master plan". This can act as a high-level report that you can share with the executives. You can find the option to insert one plan into another from the Insert menu.

Hope that helps, -Siddharth

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.